BREEAM-NL for a school building: which scheme applies?

You can have a school building assessed under BREEAM-NL. There is no separate school scheme, but education is a use function within non-residential buildings, with its own requirements. The New construction and renovation guideline for non-residential buildings v6.1.1 lists higher education and primary and secondary education separately. A new school or a major refurbishment therefore falls under the New construction and renovation scheme. An existing school that you manage falls under the In-Use scheme. Which guideline applies to your project is set out in IN111  from the Dutch Green Building Council (DGBC) . The requirements themselves are in the guideline .

Do not assume that a foreign school scheme applies. According to IN111, foreign BREEAM variants (BREEAM International) cannot be used for the Dutch market. Use the Dutch guideline.

Which scheme fits your school?

The choice follows the same logic as for other non-residential buildings. The difference lies in what you can still influence in the building.

SituationSchemeWhy
New school in developmentNew construction and renovationDesign choices can still be influenced, such as climate, daylight and materials
School building undergoing a major refurbishmentNew construction and renovationWith a major renovation, the building is essentially new
Existing school that is managedIn-Use, non-residentialThe assessment looks at the construction, management and use of the existing building
School board with several locationsIn-Use, per locationEach location receives its own assessment

What is special about a school?

The New construction non-residential guideline v6.1.1 contains requirements that apply specifically to education. Five examples:

TopicWhat the guideline requires for education
Daylight (HEA 01)Daylight according to NEN 17037 and NPR 4057. For teaching spaces, 60% of the floor area must meet the requirement for one credit and 80% for two credits
Lighting (HEA 02)In classrooms and lecture halls, the stage, walkway and audience areas can be controlled separately. The teacher can easily operate the lighting by hand
Thermal comfort (HEA 05)The minimum requirement for education is the Frisse Scholen Programme of Requirements 2021 (Healthy Schools programme), class B or A
Climate zoneFor education, each room where lessons are given is one zone
AcousticsThe starting point is at least class B of the Frisse Scholen Programme of Requirements 2021

Class C of Frisse Scholen is the basic level, class B the higher level and class A the highest. A new school that only achieves class C does not meet this minimum requirement for thermal comfort.

Example: a primary school with 8 classrooms. In each classroom, the teacher must be able to operate the lighting by hand, and the classroom must be controllable as its own climate zone.

The general points also still apply. The usage profile of a school differs from that of an office: a school is full during certain hours and days. Ask the Expert how the usage profile is taken into account in the assessment. Mobility also plays a role, such as bicycle storage and accessibility by bus.

Questions to ask in advance

Before you start a process, a short consultation helps. Below are the questions to ask DGBC or an experienced Expert. This prevents you from starting with the wrong scheme.

QuestionWhy it matters
Which use function applies to my building?Determines which guideline and which requirements apply
Is it new construction, a major renovation or an existing building?Determines the scheme
What is the gross floor area (GFA)?Determines the DGBC rates
Is a bespoke route (Bespoke) needed?For projects that do not fit the guideline

If your project does not fit any guideline, IN111 provides a bespoke route (Bespoke). This is a separate process, so ask DGBC about it early.

What goes into the file for a school?

An assessor evaluates a school on the same evidence as any other building. The difference lies in the data you must be able to provide. This list helps you build the file early.

ComponentWhat you provideCommon mistake
Building dataGFA, number of classrooms, use functionChoosing a use function without checking the application document
InstallationsVentilation plan, specifications and maintenance reportsKeeping only the quotation instead of the completed report
Indoor climateMeasurement or calculation reports for classroomsTaking measurements on a quiet day, while the school is actually full (a practical mistake, not one from the guideline)
EnergyConsumption over a full yearUsing half a year of data and presenting it as an annual figure
Management (existing school)Maintenance plan, logbook and occupancy dataWriting a plan that is not carried out in practice

Steps for a school project

Determine the phase

New construction, major renovation or existing building. That determines the scheme.

Check the use function

Does the function match the guideline? This is the most underestimated step.

Ask about costs

Read costs and timeline for the DGBC rates. The rates depend on the GFA and the type of process.

Bring in an Expert

An Expert knows the schemes and can work out the questions above for you. See the role of the Expert.

Common mistakes

  • Assuming that a separate school scheme exists. Education is a use function within the New construction and renovation or In-Use scheme. An incorrect registration costs time and money.
  • Aiming for class C of Frisse Scholen. For thermal comfort, BREEAM-NL requires class B or A.
  • Not including the existing use. For an existing school, the use belongs to management. Without usage data, a high level is difficult to achieve.
  • Starting too late. Bringing in an Expert only after the design leaves design opportunities unused. See the step-by-step plan.

Frequently asked question: does BREEAM-NL also apply to a municipal school?

The scheme depends on the building, not on the owner. A municipal school follows the same choice as a school run by a school board or foundation. The client does matter, however, because the client often sets the target level. More about the target groups is on the page who BREEAM-NL is for.