V&G plan: what must it contain?

A V&G plan (safety and health plan) is the legally required plan for a construction project. It sets out which hazards are present on the construction site and how you control them. The client must make sure it exists, under article 2.28 of the Arbobesluit (Dutch Working Conditions Decree) . In the design phase, it describes the risks of the design. In the execution phase, the contractor develops it into a plan for the construction site.

The V&G plan is therefore a legal duty under the construction rules of the Arbowet (Dutch Working Conditions Act) . It is not a VCA requirement. It does connect to the VGM plan for contractors that VCA** asks for. Below you can read when a V&G plan is mandatory, what the law says it must contain, and what a completed plan looks like.

When is a V&G plan mandatory?

A V&G plan is mandatory for two types of construction work. This is set out in article 2.28, first paragraph, of the Arbobesluit.

SituationLegal basisExample
The construction work is notifiable: more than 30 working days and more than 20 workers at the same time, or more than 500 person-daysArt. 2.27 and 2.28 ArbobesluitNew build of a school
The work involves special hazards listed in Annex II of the European construction site directive 92/57/EECArt. 2.28 ArbobesluitA small sewer job in a deep trench

Note the second row. Even a job that lasts one week can need a V&G plan if the work involves a special hazard.

Which activities involve special hazards?

Annex II of directive 92/57/EEC  lists ten types of work. In short:

No.Special hazard
1Risk of being buried, sinking into the ground or falling from height
2Exposure to dangerous chemical or biological substances
3Ionising radiation
4Work near high-voltage cables
5Risk of drowning
6Shafts, underground excavation work and tunnels
7Diving with air supply
8Work in caissons with compressed air
9Work with explosives
10Assembling or dismantling heavy prefabricated elements

Article 2.28, second paragraph, lists what the V&G plan must contain at least, “depending on the progress of the construction process”. There are seven parts.

Part (art. 2.28 para. 2)What do you write down?
a. Project detailsA description of the structure, the companies on the construction site, and the names of the design phase and execution phase coordinators
b. Risk inventoryThe specific hazards of this structure, such as asbestos, contaminated soil or water, and hazards from working at the same time or one after another
c. MeasuresWhat you do against each hazard in part b
d. AgreementsWho carries out each measure and when
e. SupervisionHow you check that the measures work
f. Design choicesStructural, technical and organisational choices for safety, with supporting reports
g. Information and instructionHow workers on the construction site are informed

The law does not prescribe a fixed format. A five-page plan is fine if all parts are included. A thick standard document without project-specific hazards is not.

V&G plan design phase and execution phase: the difference

The Arbobesluit divides the construction process into two phases. The V&G plan grows with the project, from design to execution.

Design phaseExecution phase
Who is responsible?ClientExecuting party (contractor)
Who drafts it?Design phase coordinator (art. 2.30)Execution phase coordinator updates it (art. 2.31)
What does it cover?Risks that follow from the design and the design choicesWorking methods, planning, site layout
When is it finished?Part of the specifications, before work starts on site (art. 2.32)Ongoing, updated as the work progresses

An example. In the design phase, the architect chooses prefabricated façade elements instead of brickwork at height. That reduces the risk of falling and is recorded as a design choice in the V&G plan. In the execution phase, the contractor describes how the crane places the elements, where the barrier goes and who prepares the lifting plan.

Are two or more employers, or an employer and self-employed workers, on the construction site? Then the client appoints a design phase coordinator, and the executing party appoints an execution phase coordinator (article 2.29 Arbobesluit).

Example V&G plan execution phase: risk table

The core of every V&G plan is the table of hazards, measures and responsible parties (parts b to e). Below is a fictional example for the renovation of a three-storey office building, with eight weeks of construction time and four companies on site.

HazardPhaseMeasureWhoSupervision
Falling from the roof edge when replacing the roof coveringWeek 2-4Temporary edge protection all around, no work without edge protectionRooferSite manager checks daily
Asbestos-containing sealant in window frames (from the survey report)Week 1Removal by a certified asbestos removal company before demolitionAsbestos removerClearance measurement before demolition starts
Falling objects during façade work above the entranceWeek 3-6Canopy above the entrance, walking route divertedMain contractorWeekly workplace inspection
Work at the same time: electrician under scaffolding workWeek 5Work separated in time, coordination in the site meetingExecution coordinatorPlanning in the site meeting
Lifting installations onto the roofWeek 6Lifting plan, fenced lifting area, certified crane operatorCrane hire companyCheck of lifting plan before start
Dust from grinding concreteWeek 2-7Extraction at the source, wet working, FFP3 dust mask as a last measureAll companiesSpot check during inspection

Note the order in the last row. You tackle a hazard at the source first and use personal protective equipment only as the last measure. This is the occupational hygiene strategy from the Arbowet.

V&G plan and VCA: how do they relate?

VCA does not require a V&G plan, but it does require its own VGM project plan for projects. This is set out in question 5.1 of the VCA checklist 2026/6.1  and applies to VCA** and VCA Petrochemie. In practice, they complement each other.

V&G planVGM project plan (VCA)
Legal basisLaw: art. 2.28 ArbobesluitCertification scheme: VCA question 5.1
Who is responsible?Client, then the executing partyThe VCA-certified contractor itself
ScopeThe whole structure and all companies on the construction siteThe contractor’s own work and that of its subcontractors
EnvironmentNot mandatoryPart of VGM (safety, health and environment)

As a VCA contractor, you use the client’s V&G plan as input. You take over the hazards that affect your work into your own VGM project plan and into your task risk analyses. In addition, question 3.6 of the VCA checklist requires that your workers are instructed on the client’s rules and the project plan before they start.

What does the VCA auditor check on projects with a V&G plan?

The VCA auditor does not test the V&G plan itself. They check how well your company works with it. Expect these questions during the VCA audit:

  • Is there a current VGM project plan, and does it match the client’s V&G plan?
  • Were workers and subcontractors instructed before they started, with an attendance list as proof?
  • Do workers on the construction site know the main hazards and measures?
  • Are workplace inspections carried out on the points in the plan?

Frequently asked questions about the V&G plan

Is a V&G plan mandatory for a renovation?

Yes, if the renovation is notifiable or involves a special hazard from Annex II. A small renovation without those characteristics does not need a V&G plan. The employer must still have a RI&E (risk inventory and evaluation) and work safely.

Who pays for the V&G plan?

The client is responsible for the plan in the design phase. It must form part of the specifications (article 2.32). The costs of updating it in the execution phase usually lie with the executing party, depending on the contract.

What is the difference between a V&G plan and a V&G file?

The V&G plan covers the construction phase. The V&G file (article 2.30, under c) gathers information for later work on the building, such as maintenance or demolition. Think of the location of anchor points on the roof.