Infrastructure toolbox meeting: example, topics and recording

A toolbox meeting in infrastructure (infra) is a short discussion of a safety risk that arises when working along a road, on a railway, in a tunnel or at a flood defence. You discuss one topic for 10 to 30 minutes with the crew, and record it with the date, location and signatures. The VCA requirement for toolbox meetings also applies in infrastructure. For how often you must hold them, read the page toolbox meeting VCA. Link the topic to the project’s VGM plan (Safety, Health and Environment plan) or V&G plan (Safety and Health plan).

For the general explanation of the toolbox meeting and how it differs from an LMRA (last-minute risk analysis), see the same page. This page covers the practice in infrastructure: which topics you choose, what a completed example looks like and what the auditor wants to see.

Which topics suit infrastructure?

Work in infrastructure carries risks that rarely occur in an office or factory. Think of traffic passing the workplace, work on a railway line with train movements, excavation near cables and pipes, and work near water. For each toolbox, choose one risk from your team’s work location.

CategoryExample topicWhy it suits infrastructure
TrafficBarriers and traffic controllers for work along the roadPassers-by and lorries are the biggest source of risk
RailwayWorking near a railway lineA train arrives sooner than you expect
GroundDigging near cables and pipesA damaged cable or pipe is immediately dangerous
HeightWorking on a scaffold or cherry picker in an open environmentWind and ground conditions change from day to day
SeasonWinter work: slippery surfaces and reduced visibilityThe risk differs from month to month

This is a rule of thumb, not an official list. Preferably choose a topic that appears in your incident register, rather than one you read about somewhere.

Example: toolbox meeting on working next to a railway line

The example below is fictitious. It shows how to build up the toolbox and record it.

PartEntry
Date and time14 March, 07:00
LocationWork area on railway, km 42.3
TopicWorking next to a railway line
Given byForeman Jansen
AttendeesFour employees, with signature
Duration15 minutes

Introduction (2 minutes). Explain why this topic matters today. For example: “Last week we were close to a passing train. Today we discuss how to prevent that.”

Risks (4 minutes). Ask the group what could go wrong: a train you do not hear, tools falling onto the track, a colleague standing too close to the rails.

Measures (5 minutes). Discuss the agreements for the workplace: who keeps watch, which signal applies when a train approaches, and where the safe place is.

Practical question (3 minutes). Ask the question: “What do you do if you hear a train approaching and you are standing with your tools in the wrong place?”

Closing (1 minute). Summarise the core in one sentence: “We always look at the track before we put a tool down.”

The order is a tool, not a required format. Adjust the time for each part to suit the group. The rules for working on or next to the railway are set by the railway manager; this example does not replace them.

What do you record for the audit?

You must record every toolbox. Without a record, it does not count towards the audit. The minimum is:

  • Date and location
  • Topic of the toolbox
  • Name of the person who gave the toolbox
  • Attendance list with signatures

The signatures are the most important part. An attendance list without signatures does not prove that the employees were present. Keep the records and link them to the work area or project, so that the auditor can see how they are spread.

A record per location helps during the audit. If the toolbox was held on a project in infrastructure, also note the project number. That way the auditor can link the toolbox to the relevant VGM plan or V&G plan.

Checklist for your next toolbox

Go through these points before you start the toolbox. Then everything is ready and the discussion stays short.

  • Did you choose the topic based on a recent incident, a near miss or a risk at this work area?
  • Do you know the workplace agreements, such as the watch, the safe place and the signal when something approaches?
  • Do you have a photo, drawing or an object from the location to hand?
  • Is the attendance list ready for signatures, with the date and location already filled in?
  • Have you noted who gives the toolbox, so that the record is complete?

Common mistakes

  • The same toolbox over and over. An auditor sees that the topics do not vary, and that counts as weak.
  • Too much theory. Let the crew think along with a photo or a real object from the workplace.
  • No link with the incident register. If there was a recent near miss at this work area, discuss it at the next toolbox.
  • A long presentation. A screen full of text often makes the group lose interest. A map or a drawing works better.

Frequently asked questions

Must an infrastructure company choose different topics from a construction company? Not required, but the risks differ. In infrastructure, traffic and railways more often play a role. Choose topics that match the work of your crew.

Can the toolbox also be held at the work area itself? Yes, and that is often the best moment. Hold the discussion at the place where the risk arises, as long as that is safe.

Who may give a toolbox? It does not have to be the board of directors. A foreman or an experienced employee can give the toolbox. Always note who gave it.

More information

  • Toolbox meeting VCA - frequency, recording and general topics
  • LMRA - the personal check just before the task
  • V&G plan - the plan for construction work, under which much infrastructure work falls
  • VGM plan - the project plan for contractors