Energy performance indicators (EnPIs) are the KPIs of your energy management. They show whether your energy performance is improving. Under ISO 50001:2018 , EnPIs are mandatory (chapter 8.2): you define them, report them periodically and compare them with your energy baseline. The NEN publication  of the standard describes EnPIs as “quantitative values or measures of energy performance”.

A good EnPI answers the question: are we becoming more efficient? Not “are we using less?” (that can also happen because you produce less), but “are we using less per unit of output?”

What is an EnPI under ISO 50001?

An EnPI (Energy Performance Indicator) is a measurable value that shows how efficiently you use energy. It is almost always a ratio: energy use divided by a relevant unit.

Formula: EnPI = energy use ÷ relevant variable

Examples:

  • kWh per product produced
  • MJ per m² of floor area
  • GJ per FTE
  • PUE (total use ÷ IT load)

The EnPI normalises your use. If production grows and your absolute use rises, but your EnPI (kWh/product) falls, you become more efficient. That is what counts.

ISO 50001 EnPIs per sector: practical examples

Production companies

EnPIUnitTypical valueGood target
Electricity per productkWh/piece5-50 kWh/piece-10% to -20% in 3 years
Gas per productm³/piece0.5-5 m³/piece-10% to -15% in 3 years
Compressed air per productm³ air/piece2-20 m³/piece-15% to -25% in 3 years
Specific usekWh/kg output0.1-10 kWh/kgDepends on the sector

Example: A metal company measures 12 kWh per produced part. After investing in frequency controllers and compressor optimisation: 10.2 kWh per part. Improvement: 15%.

Data centres

EnPIUnitTypical valueGood target
PUE (Power Usage Effectiveness)Ratio1.4-1.8Below 1.3
kWh per rackkWh/rack/year15,000-50,000-10% in 3 years
Cooling efficiencykW cooling/kW IT0.3-0.6Below 0.3
WUE (Water Usage Effectiveness)L/kWh0.5-2.0Below 1.0

Example: A data centre has a PUE of 1.58. By introducing free cooling and hot/cold aisle containment, the PUE improves to 1.34. Saving: 15% on total energy use.

Office buildings and property

EnPIUnitTypical valueGood target
Electricity per m²kWh/m²/year40-120 kWh/m²-15% in 3 years
Gas per m²m³/m²/year5-15 m³/m²-15% in 3 years
Energy per FTEGJ/FTE/year5-20 GJ/FTE-10% in 3 years
Energy per workstationkWh/workstation/year1,500-4,000-10% in 3 years

Example: An office building (10,000 m²) uses 85 kWh/m². After LED lighting, smart thermostats and daylight control: 68 kWh/m². Improvement: 20%.

Hotels and hospitality

EnPIUnitTypical valueGood target
Energy per overnight staykWh/guest night15-60 kWh-10% to -20% in 3 years
Gas per overnight staym³/guest night2-8 m³-10% in 3 years
Energy per m²kWh/m²/year100-300 kWh/m²-15% in 3 years
Swimming pool per m³ of waterkWh/m³/day5-15 kWh/m³-20% in 3 years

How do you choose the right EnPIs for ISO 50001?

Not every EnPI is suitable. A good EnPI meets three criteria:

CriterionExplanationGood exampleBad example
RelevantSays something about your core activitykWh per productkWh per office visitor
InfluenceableYou can improve the valuekWh per m² (insulation helps)kWh per degree day (you cannot control the weather)
MeasurableYou have the data (or can get it)kWh per building (meters in place)kWh per customer (hard to measure)

How many EnPIs do you need?

OrganisationNumber of EnPIsExplanation
Small (1 location, homogeneous)2-4One per energy type plus one overall
Medium-sized (several departments)4-6At least one per SEU
Large (several locations)6-10Per location plus overall

Rule of thumb: At least one EnPI per significant energy aspect (SEU). If compressors are an SEU, you need an EnPI for compressor efficiency (for example kWh per m³ of compressed air).

Reporting and monitoring EnPIs

Reporting frequency

FrequencySuitable forAdvantage
MonthlyMost companiesSpots deviations quickly
WeeklyEnergy-intensive processesOperational control
QuarterlyOffices, propertyLess administration

The auditor expects at least quarterly reports. Monthly is better: you spot deviations sooner.

Setting up a dashboard

Your EnPI dashboard shows per indicator:

  • Current value (this month or quarter)
  • Baseline (reference value from the energy baseline)
  • Target (target value from your action plan)
  • Trend (line over 6-12 months: is it moving in the right direction?)

Tools: Excel works for small organisations. For medium-sized and larger organisations, consider energy management software (Metrix, EnergyCAP, Power BI dashboards). Costs: €1,000-€10,000 per year.

What do you do when an EnPI deviates?

If an EnPI rises unexpectedly (gets worse):

  1. Check the data. Is the measurement correct? Is the meter calibrated? Is the production data correct?
  2. Find the cause. New machine? Change in process? Leak? Fault?
  3. Take action. Solve the problem or adjust your action plan.
  4. Document. Record what happened and what you did. The auditor will ask for it.

Common mistakes with EnPIs under ISO 50001

Measuring only absolute use

“We used 480 MWh” is not an EnPI. That is a meter reading. An EnPI normalises: 9.6 kWh per product. Without normalisation, you cannot draw conclusions about efficiency.

Defining too many EnPIs

Tracking 15 EnPIs takes a lot of time and adds little insight. Focus on 3-8 indicators that you actually use for decisions.

Defining EnPIs but not reporting them

You defined good EnPIs at the start, but after six months nobody looks at them. The auditor asks for trend data. Without reporting, that is a finding.

Choosing the wrong normalisation variable

kWh per FTE for a production company says little, because FTEs have little relation to energy use. kWh per product is better. Choose a variable that actually drives the use.

EnPIs and the rest of ISO 50001

ComponentRelation to EnPIs
Energy reviewProvides the data to define EnPIs
SEUsEach SEU gets at least one EnPI
Energy baselineYou compare EnPIs with the baseline
ObjectivesTargets are expressed as EnPI improvement
AuditAuditor checks whether EnPIs are measured, reported and used
Management reviewEnPI trends are a fixed agenda item