Knowledge baseWriting an audit plan

Audit plan example for an internal audit (ISO 9001)

An audit plan is the plan for one specific audit: which processes and requirements you check, who you speak to, when it takes place and which evidence you look for. It belongs to your annual programme for internal audits. After the audit, you record the findings in the audit report. ISO 9001 requires you to define the criteria and scope for each audit (clause 9.2.2). The audit guideline ISO 19011 describes how to build an audit plan. It is guidance, not a requirement, so you may use your own format as long as the audit is repeatable.

ISO 19011 has been available in a new edition since May 2026 (ISO 19011:2026), which replaces the 2018 edition. You buy the guideline from NEN (Royal Netherlands Standardization Institute) . Check there which language version is available.

An audit plan differs from the annual programme. The annual programme states which area you audit in which quarter. The audit plan states exactly what you will do in one day.

Audit plan and annual programme side by side

FeatureAnnual programmeAudit plan
ScopeThe whole management system over a year or cycleOne audit: one department, process or part of the standard
Time frameMonths or the whole yearOne day or a few hours
Who writes itThe person responsible for the audit programmeThe auditor, often in consultation with the auditee
What it containsAreas, dates, auditor, statusTimes, topics, requirements, contacts, evidence
When it is finishedAt the start of the cycleBefore the audit, shared with the auditee

Do not have an annual programme yet? Start with that first. You build the audit plan on top of it.

What goes in an audit plan?

A useful audit plan has six parts. Keep it short: two A4 pages is enough for one day of audit.

PartWhat you fill inWhy it matters
Purpose and scopeWhich process or department, and which standardPrevents you from auditing everything and nothing
CriteriaThe requirements you test, per standard clauseThe auditor knows what you measure against
Audit team and auditeeWho audits, who is the contact personIndependence and preparation
Date and timesA time slot per topicRealistic and checkable
Topics and evidenceWhat you want to see: records, conversations, observationsMakes the audit concrete
Distribution and reportWhen the summary followsClosing and follow-up

Example: audit plan for one day of internal audit

A small bakery with 25 employees wants to audit the purchasing and supplier management process. The plan below shows what this could look like. The standard is ISO 9001:2015. The numbers in the “criteria” column are clauses of that standard. Use the structure and replace the content.

TimeTopicCriteria (ISO 9001)Contact personEvidence you look for
09:00 - 09:15Opening and confirming scopeClause 4.4: processes of the management systemOwnerProcess description for purchasing
09:15 - 10:00Supplier assessmentClause 8.4: externally provided products and servicesPurchasing employeeAssessment list, list of approved suppliers
10:00 - 10:45Sample of purchase ordersClause 8.4: control of what you purchasePurchasing employeeTen order forms with checks
10:45 - 11:15Nonconformities on receiptClause 10.2: nonconformity and corrective actionWarehouse employeeNonconformity register, correction
11:15 - 11:45Competence of the buyerClause 7.2: competenceOwnerTraining overview
11:45 - 12:00Closing and first findingsAll chaptersOwnerNotes

Note: the plan names evidence, not a judgement. You write down what you want to see, not what you already think.

An audit plan is not a checklist. The checklist contains the questions you ask. The audit plan says when and to whom you ask them. Use both: the plan as an agenda, the checklist as a memory aid.

Step by step: writing an audit plan

Choose the topic and the scope

Take the topic from your annual programme. Write in one sentence what you audit: “the bakery’s purchasing process, including supplier management”. Without a scope, the audit runs out of control.

List the criteria

Take the standard and note the clauses that are relevant to this process. For a combined audit against several standards, combine the clauses, because many requirements overlap.

Decide the evidence per criterion

For each criterion, ask yourself: which record exists, who can show it to me, and what will I observe? If you look for a supplier assessment list in supplier management and cannot find one, that is a finding for the audit report.

Plan the times and conversations

Allow at least 30 minutes per conversation and keep a buffer at the end. Schedule conversations with the people who do the work, not only with the line manager.

Send the plan to the auditee in advance

A plan shared the week before gives the auditee the chance to prepare the evidence. That is fair, and it prevents noise during the audit.

Record what has changed

If something different emerges during the audit, write it down in the plan or the report. The audit plan is a working document, not a contract.

What does the auditor look for in your audit plan?

An external auditor looks not at the format but at whether your audit really examines the organisation. They look at these points:

  • A clear scope that matches the annual programme.
  • Criteria that refer to the right clauses of the standard.
  • Conversations with employees who do the work, not only with the manager.
  • Evidence you will actually review: records, orders, logs or measurement data.
  • A report that refers back to the plan, so it is visible what was not done.

Common mistakes in the audit plan

Everything in one day. A whole management system does not fit into one audit. Spread the scope across the cycle.

Only conversations, no evidence. “Yes, we always do that” is not evidence. Ask for the record or observe the process.

The auditor audits their own work. An internal auditor does not check what they have done themselves. ISO 9001 requires the auditor to be objective and impartial (clause 9.2.2). See planning and carrying out internal audits.

No link to findings from last time. Include open actions from the previous audit and the management review in the plan.

The plan is not shared. A secret plan produces no improvement. Share it, even if it is short.